NamWater finalises ESIA for desalination, power plant project

Home Uncategorized NamWater finalises ESIA for desalination, power plant project
NamWater finalises ESIA for desalination, power plant project


The Namibia Water Corporation Ltd (NamWater) says it has completed a final environmental and social impact assessment (ESIA) for its large-scale desalination and power plant project along the central coast, with an estimated investment of N$4.2 billion.

The draft ESIA report, which was open for public review from 22 September to 23 October 2023 (extended to 6 December 2023), has now been updated to a final ESIA report.

It was submitted for approval to the Ministry of Environment, Forestry and Tourism, the Ministry of Agriculture, Water, and Land Reform, and the Ministry of Mines and Energy.

This comes as the project, which will be rolled out in phases, aims to enhance water security and power generation in the region.

Phase 1 of the project, encompassing the construction of a desalination plant, water carriage system, and associated infrastructure, is expected to cost N$3 billion, while the full-capacity plants, including the Gaingu PV power plant and associated infrastructure, will cost N$4.2 billion.

The ESIA process, led by Environmental Assessment Practitioner SLR Environmental Consulting (Namibia) (Pty) Ltd, estimates that approximately 200 temporary jobs will be created during the construction phase.

Furthermore, indirect and induced employment opportunities are anticipated to arise from the utilisation of Namibian and Southern African Development Community (SADC) products and services.

“The primary objective of the project is to deliver potable water, desalinated from seawater at the coast, to the central coastal area through the existing water transmission system. The development plan involves the construction of a new 4km water pipeline connecting the desalination plant to the Omdel-Swakopmund pipeline, with a total capacity projected to reach 36.2 million m³ per annum,” stated the report.

In addition, SLR notes that the project proposes the establishment of a photovoltaic (PV) solar installation with a cumulative capacity of 35.10MWp, known as the Gaingu PV Power Plant.

“This solar facility will not only provide power to the desalination plant and pump station but also contribute to the broader energy grid. A new 33kV transmission line will connect the Gaingu PV Power Plant to the existing New Khan substation,” noted the firm.

The draft ESIA report outlines that about 50 people will be required to operate the desalination plant during its operational phase.

The report suggests a Design-Build-Operate-Transfer model of ownership, aligning with NamWater’s objective to minimise construction and operation risks while maximising efficiency. A similar model is proposed for the Gaingu PV Power Plant, with the engagement of an Independent Power Producer.

The project comes as declining underground water reserves in the coastal area are putting immense pressure on NamWater to maintain an uninterrupted water supply.

The desalination plant is set to supply towns such as Henties Bay, Swakopmund, and Walvis Bay, Arandis, Uis, and settlements in Daures, with aspirations for water supply to the capital city, and in the long run, Botswana.

This large-scale infrastructure project is expected to significantly enhance water security and power generation in the central coastal region of Namibia, addressing the growing challenges of water scarcity and energy demand.



Source link

Leave a Reply

Your email address will not be published.